The critical path is the path in the network with the greatest amount of risk.
4. A network-based schedule has four paths, namely 7, 8, 9, and 10weeks. If the 10-weekpath is compressed to 8 weeks, then:
A. The forward pass going beyond the customer's end date and the backward pass is measured from the customer's end date
The critical path is the path in the network with the greatest amount of risk.
The critical path can be completed before the customer’s desired end date
Negative slack is the result of: The forward pass going beyond the customer’s end date and the backward pass is measured from the customer’s end date. Non-critical-path activity using up all of their slack. The critical path can be completed before the customer’s desired end date.