which of the following is true about net initial investments course hero

by Prof. Freddy Funk PhD 7 min read

When a project’s net present value exceeds zero?

When a project's net present value exceeds zero, then: a. the project should be accepted b. the project will be acceptable using the payback period method c. the IRR should be calculated to ensure that the project's IRR is less than the cost of capital d. both a and c are true

What is the required return on investment for a firm?

A firm is evaluating a proposal which has an initial investment of $50,000 and has cash flows of $15,000 per year for five years. If the firm's required return or cost of capital is 15%, should it accept the project using

When a project has a negative NPV its IRR is?

c. If a project has a negative NPV, its IRR will always be less than the cost of capital. d. There is sometimes a conflict between NPV and IRR in the case of mutually exclusive projects. e. all of the above are correct E. all of the above are correct 66.