which of the following correctly calculates the early finish for an activity course hero

by Alda Lehner 7 min read

What is the predecessor of activity 1?

Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of

When completing a backward pass, do you carry the LS to the next preceding activity?

When completing a backward pass, you carry the LS to the next preceding activity to establish the LF, unless the next preceding activity is a burst activity, in which case you select

Is activity 1 a predecessor for activity 2?

Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of. Having more than one start node. Looping.

When can an activity begin?

A. An activity cannot begin until all preceding activities have been completed

What is the predecessor of activity 1?

Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of

When can an activity begin?

A. An activity cannot begin until all preceding activities have been completed

Is activity 1 a predecessor for activity 2?

Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of. A. Conditional statements.