If a project has more than one activity that can begin when the project is to start, a common start node should be used to indicate a clear project beginning on the network. Without a common start node, each path is a. Multiple start path. Confused path. Parallel path.
Tom is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days. Fortunately, Tom has 10 days of slack; however, he shares this slack with the hardware installer.
Fortunately, Tom has 10 days of slack; however, he shares this slack with the hardware installer. He will have to let the contactor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days. Tom and the installer share 10 days of. Free Slack.
Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of. Having more than one start node. Looping.