what is the main technique used for validating scope? course hero

by Sabryna Osinski 5 min read

What is the main technique used for validating scope give an example of scope validation on a project?

The only technique used for validating scope is inspection. Inspection entails reviewing the deliverables to make sure they meet the stakeholder needs.Mar 26, 2016

What is the process used to validate scope?

Validate Scope is the process of formalizing acceptance of the completed project deliverables. The key benefit of this process is that it brings objectivity to the acceptance process and increases the chance of final product, service, or result acceptance by validating each deliverable.

What does validate scope mean?

formalizing acceptance"Validate Scope is the process of formalizing acceptance of the completed project deliverables." "Control Scope is the process of monitoring the status of the project and product scope and managing changes to the scope baseline." PMBOK® Guide, pp.Jun 29, 2019

When should validate scope be done?

Answer: At the end of each phase of the project The Validate Scope process occurs during project monitoring and controlling. It is done at the end of each project phase to get approval for phase deliverables, as well as at other points to get approval for interim deliverables.

What is the only tool and technique used during scope verification?

validation process. What is a tool and technique used during scope validation? scope.

Which process group includes the Validate scope process?

Monitoring & Controlling process groupValidate Scope, which is part of the Monitoring & Controlling process group, is a tricky process and many test takers easily confuse this with other processes. In this process, the customer is formally accepting the completed project deliverables.

Which of the following is a main input for scope validation?

The scope management plan, scope baseline, requirements documentation, requirements traceability matrix, validated deliverables, and work performance data are the main inputs for scope validation. The main tools for performing scope validation are inspection and group decision-making techniques.

Which is a vital output of validate scope process?

Project document updates and work performance information are other outputs of the validate scope process. After deliverables are completed and accepted, project documents must be updated and also accepted deliverables must be marked in the project documents.Jan 2, 2022

What is the first step in project scope management?

The first step toward defining project scope is to create a statement of work. A statement of work is the official document that outlines the requirements for a particular project. It includes a general description of the work requested, a timeline, a schedule, any special skills necessary and the work location.Sep 12, 2021

How do you validate a project?

A validation project usually follows this process: Validation Planning – The decision is made to validate the system. A project lead is identified, and validation resources are gathered. Requirement Gathering – System Requirements are identified.

How do you validate project requirements?

Validating Requirements – How do I know I'm not missing anything?Start with Good Scoping of the Effort.Break Down Scope into More Detailed Business Requirements.Get Into the “How” with Functional Requirements.Thinking About Test Cases Will Help Fill in Any Remaining Gaps.Take a Walk In The Test Data.Put It All Together.More items...•Aug 1, 2016

How do you control the scope of projects?

The process of controlling scope involves many objectives that are to be met; the following criteria from the Project Management plan will help in managing scope.Scope Management Plan. ... Requirements Management Plan. ... Change Management Plan. ... Configuration Management Plan. ... Scope Baseline. ... Performance Measurement Baseline.Jun 29, 2021