Mar 15, 2021 · All of the following actions occur in the direct and. 4. All of the following actions occur in the Direct and Manage Project Work process except which of the following? a. Adapt approved changes into the project’s plans b. Collect and document lessons learned c. Determine the project life cycle for the project d. Staff, train, and manage ...
Q9: All of the following are parts of the Direct and Manage Project Work process except: a) Identifying changes b) Using a WBS c) Implementation correction actions d) Setting up a project control system. Q10: The primary customer of a project has requested an application change during use testing.
A project manager is leading a process improvement project for a factory operation. Currently, the project manager and the team are performing the Monitor and Control Project Work process. Which of the following activities might the project manager and the team conduct during this process? Select one: a. Analyzing change requests and either approving or rejecting them b.
The completion of project planning process is the major input for starting direct and manage project work process. Because, once the project plan is finalized, the executing process group starts to implement the project activities which are planned in project planning.Jan 2, 2022
Following are the outputs of monitoring and controlling project work: Change Requests. Work Performance Reports. Project Management Plan Update.May 22, 2019
Which of the following is NOT an output of Monitor & Control Project Work? This question is basically asking you the difference between Change Requests and Change Request Status Updates. Change Request Status Updates are outputs from Perform Integrated Change Control, not Monitor & Control Project Work. 178.
The project plan execution represents the majority of the project budget.
Ans. (b ) Producing automobile tires is not considered as a project.Oct 23, 2019
Answer: BExplanation: Activity Resource requirements is a primary input to Develop Human Resource Plan process.Nov 9, 2017
The outputs of the "Manage Stakeholder Expectations" process include: organizational process updates, change requests, project management plan updates, and project document updates.
There are two main outputs from the identify stakeholders process namely; the stakeholder register and the stakeholder management strategy.
The project charter is an output of the Develop Project Charter process. The project charter is an input to which process? All of the following are NOT inputs to Monitor and Control Project Work EXCEPT: A Approved change requests.
The project management plan is the formal document used to manage and control project execution.
The purpose of a project management plan (or PMP) is to determine the project outcome, how a successful outcome will be achieved, who will be involved in the project, and how the project will be measured and communicated.Dec 2, 2021
Through initial project coordination, the NCDOT Project Manager should be able to understand the problem, including its history and context; define the project and the limits of what it can cover; explore the characteristics of the human and natural environment; identify potential issues and constraints; discuss ...May 29, 2019